STANDARDS OF PROOF
A brief resource - Construction Claims
Robert G. Armando, President, Tectonics, Inc.
rga@tectonicsystems.com
631-220-1098

Download This Page as a PDF File - Click Here

Tectonics, Inc. HOME PAGE   Contact Tectonics, Inc. today

BACK to White Papers & Briefs | BACK to Construction Claims

The standard of proof should be distinguished from the question of who bears the burden of proof. In civil actions, including construction claims arising from delay or acceleration, the standard of proof is relaxed to "a preponderance of the evidence". The preponderance standard simply means that the proponent of a claim must present the greater weight of the competent, persuasive evidence, even if that is only 51% of the evidence.

One further distinction that has been drawn by the courts and boards touches on the quantum of proof required for causation of delay, and the quantum of proof relating to the amount of damages. Generally, a greater certainty is necessary for proof of the causation of delay than for proof of the amount of damages.

The U.S. Court of Claims has held, in Wunderlich Contracting Co. v. United States, 351 F.2d 956, 173 ct. cl. 180 (1965) :

See also Dale Construction Co. v. United States, 161 ct. cl. 825 (1963).

Once entitlement is established, damages will not be refused solely because the contractor has not proved their amount to a mathematical certainty. Most courts and boards are willing to accept a reasonable estimate or a logical method of calculation.

See: Peter Kiewit Sons Co. v. Summit Construction Co., 422 F.2d 242 (8th Cir. 1969; and Lauria Bros. & Co. v. United States, 369 F.2d 701 (1966).


BACK to White Papers & Briefs | BACK to Construction Claims

DUTY TO COORDINATE THE WORK OF
MULTIPLE PRIME CONTRACTORS

The Owner in a multi-phase project is under a duty to coordinate the work of all prime contractors. The law requires the Owner to schedule and execute the work of the various prime contractors in a normal and reasonable sequence of construction events. The courts have allowed recovery to the delayed prime contractor where the Owner has allowed another prime contractor's work to delay access to the site or even where the Owner's failure to accelerate preceding contractors has caused a delay in the receipt of access to another prime contractor.

BACK to White Papers & Briefs | BACK to Construction Claims

DELAY, DISRUPTION, LEARNING CURVES

Analysis and comparison of project schedules is the best means of determining the impact of delays or disruptions upon a construction project. A compensable delay is one for which the Owner is responsible. The delay or disruption may be shown by comparison of the various project schedules. The impact of "pure" delay is usually readily assessable, but extended or numerous minor delays, and the effect of other disruptions also have impacts which may be demonstrated by schedule analysis. Loss of "learning curve" efficiencies is a common impact of Owner disruption. Here, actual labor costs and estimated labor costs applied under the "As- Planned" schedule are extremely helpful. Loss of labor efficiency is another impact of disruption readily demonstratable through use of project schedule analysis. Working under adverse weather conditions, overtime hours, etc. all contribute to inefficiency and result from delay or other disruptions.


BACK to White Papers & Briefs | BACK to Construction Claims

EFFECT OF OWNER APPROVALS & ACQUIESCENCE

If the Owner advertises a Pre-Bid Schedule or does not reject or raise timely objections to an "As-Planned" Schedule submitted by a contractor, it will be bound by the schedule and expected to meet its obligations thereunder.


BACK to White Papers & Briefs | BACK to Construction Claims

DUTY NOT TO DELAY, HINDER, OR INTERFERE
WITH PERFORMANCE

For years, courts have held that all parties to a contract have an implied duty to refrain from delaying, hindering, or interfering with others in the performance of their contracts. Numerous cases have found Owner liability for violation of this implied duty to the contractor. Where the Owner was unreasonably slow in providing the required access, failed to provide adequate advance planning, or committed numerous other negligent errors which contributed to unnecessary delay, the courts have found that the Owner breached its implied obligation not "to unreasonably interfere with or delay the contractor's performance". Likewise, in a number of cases, the failure to provide adequate plans and specifications, or the failure to make timely delivery thereof, constituted breach of duty.


BACK to White Papers & Briefs | BACK to Construction Claims

SUPERIOR KNOWLEDGE CREATES DUTY TO
DISCLOSE MATERIAL FACTS PRIOR TO BID

The Courts and Boards of Contract Appeals have uniformly held that an Owner, with superior knowledge as to a material fact likely to impact a bidder's cost or schedule of performance, who fails to disclose completely and accurately such information to bidders of record, shall be deemed to have breached the contract; the contractor will be paid for damages resulting therefrom under the "constructive change" theory. This would include the witholding of material facts regarding (1) schedules of other prime contractors and (2) design defects known to the Owner at the time of bid. It includes the witholding not only of technical information, but non-technical information which is critical to the bidder's cost or schedule performance.

 BACK to White Papers & Briefs | BACK to Construction Claims